Fact. MEC forecasts a load growth that cannot be covered by existing energy sources, approximately 30 – 60 MW of dedicated power to avoid paying for this power in the open market. This affects reliability and affordability. Power purchased from the open market is more expensive.
Power supply
Fact. Solar cannot produce power at night or when it rains. Essentially, solar has two costs – what it costs to build a solar field plus the cost to purchase power when there is no solar energy available for use.
Fact. The plans for solar, battery energy storage systems, and natural gas turbines were included in the 2017, 2020, and 2023 IRPs. The 2026 IRP will be completed in late 2026.
Fact. AEPCO follows the Arizona Administrative Code procurement methods approved by the ACC. AEPCO and MEC conducted multiple solicitations. The All-Source RFP was completed in 2023; the combination of solar, battery, and natural gas turbines were the most affordable option while providing the most reliable power supply. The first solar, battery storage, and LM6000 resources have already been built throughout AEPCO’s service territory.
Fact. MEC is short 30 MW of dedicated power which equates to approximately 9,500 homes and businesses being short of power. Also, MEC’s existing 30 MW of solar and battery does not provide sufficient power at night and during rainy weather, which adds another 9,500 homes and businesses that can only use “temporary power.” This situation could lead to an outage.
9,500 + 9,500 = 19,000 homes without power
The current energy markets cannot be relied upon for power supply or to be available at an affordable cost.
Myth. The generating facility is not being built to sell power to California; the facility will serve MEC and AEPCO. All power sales and transactions between or across electric utilities utilize a transaction tagging process regulated by federal agencies and reported to the North American Electric Reliability Corporation (NERC) and Federal Energy Regulatory Commission (FERC) to track the physical path of energy. They have trackable sales and can be audited to prove that power from Mohave Energy Park was sold to MEC.